100%. Langan is like a report mill.

I don’t have enough info to say whether there is negligence on the part of Langan in this instance. Temporary work shutdowns from CAMP happen on jobs. Which it sounds like you know. Especially when you are working with potential mercury vapor—which is a lot higher stakes than typical CAMP monitoring analyses. I haven’t read the RAWP but I assume the threshold levels are very low.

2

[deleted] t1_isku9d5 wrote

[deleted]

1

joelekane t1_isl5lok wrote

Agreed. But to be clear—the project was shut down for one day for CAMP issues. This long term shutdown is unrelated.