OakBelly t1_j06z9x0 wrote
Tl;dr $155k to get power and a second 3” conduit (for comm.) 2,250 ft. underground. Here’s the breakdown of a project from this past summer. GMP charged $42k to go 2250’ underground. $12k of that was for cost sharing because this was an extension to an existing underground line. There were 4 peds and one 25kva transformer. Another company was hired to trench and install two 3” conduits the entire 2250’ length. That was about $98k of which $39k was conduit @ $8/ft. A 3rd company was paid about $15k to blast 200’ of ledge for the trench.
Legitimate-Future255 t1_j09pgk7 wrote
Yowsers!
tom_echo t1_j0hgkdx wrote
Wow, why not just go above ground at that point?
8valvegrowl t1_j0i7p8y wrote
Expensive, to be sure, but running above ground has it's own risks and future costs, it's a gamble. And if you can afford to bury it correctly, then bury.