PsuedoSkillGeologist t1_j7kdcqk wrote
Reply to comment by KingofthisShit in MTA spent twice as much on Second Ave subway consultants as it did on its construction by NYY657545
More oversight?
I take it you don’t work construction.
Much less NYC Construction.
Why would an owner care if you overstaff your job? They don’t pay them. In fact they prefer you overstaff it. You’re paid based on a schedule of values. Not your staffing.
The consultant fees (mine included) is a result of change orders. The only reason the MTA was on the hook for it was because the GC was able to prove, through the help of the consultants, that the owner provided insufficient information to make a reasonable bid.
As per usual, the owner and misappropriation of their funds is what cost the city more money. Not the contractor and consultants.
SuperTeamRyan t1_j7khnfk wrote
I was under the impression the consultant should be the one providing the information to the contractor and the state(owner) pretty much just says we want X done. At this point in my understanding all the contractors make impossibly low bids to get the job and then once the have the job delay slow and stall work to milk the project because the state compared to them generally have unlimited funds and they know the state will not allow a public works project to just stall out once ground has been broken.
airvqzz t1_j7kj9l9 wrote
Not how it works at all
Jeff3412 t1_j7kzrw7 wrote
>I was under the impression the consultant should be the one providing the information to the contractor and the state(owner) pretty much just says we want X done.
Correct. I am a design consultant.
We meet with clients, architects, or owner reps and ask them what their needs are with regards to our trade and then we make specs and drawings that go out to bid to contractors. Depending on the job and contract we may help review the bids and point out which bids are missing scope where.
>At this point in my understanding all the contractors make impossibly low bids to get the job and then once the have the job delay slow and stall work to milk the project because the state compared to them generally have unlimited funds
A contractor winning a job with too low of a bid (whether intentionally or unintentionally) and then trying to create as many change orders as possible even in places that the documents are clear is always a concern, but public sector jobs are usually worse because often legally they have to go with the low bid.
In the private sector you can say to the end client, the architect, or owner's rep that contractor X has a slightly lower bid than contractor Y but based on past jobs contractor Y is more reliable (and their bid is actually capturing all their needed scope). Then the client can choose to spend slightly more upfront to pick the contractor that their consultant advised them too.
But on a public job letting agency officials pick a higher bid could also end up being a recipe for enabling corruption.
mrpeeng t1_j7l5gqg wrote
My old company did this for various gov. inspection jobs. They'd undercut the bids just to win them for the cash flow to pay for other higher paying jobs. Gov. payment was always reliable so that kept the business running when it was slow. When they lost a job to some one else due to a lower bid, they'd have them audited to see how it was possible and fight it. There are a bunch of stupid rules that inflate the bids though like some jobs had requirement where you HAVE to use a company that is women owned for 20% of your supplies. You find them and they ALL charge 200% the normal rate of something like a ream of paper.
atyppo t1_j7lc1fd wrote
Yep. It's insane. If the government is literally required to discriminate 30% of the time (NYS standard) for MWBE owned businesses, then I have no hope for our legislators, since they clearly lack any sort of self-awareness. Shocking news: women aren't typically particularly interested in running tunneling companies, for example (yes, I'm aware this is a very simplified example). The ones that are can now charge whatever they want since they have little to no competition, yet the state is obliged to contract them.
vidro3 t1_j7lcixd wrote
> In the private sector you can say to the end client, the architect, or owner's rep that contractor X has a slightly lower bid than contractor Y but based on past jobs contractor Y is more reliable (and their bid is actually capturing all their needed scope). Then the client can choose to spend slightly more upfront to pick the contractor that their consultant advised them too.
Isn't the standard something like lowest qualified bid or lowest responsible bid? I forget the exact wording. I've definitely seen bids for city projects that all came in a pretty tight range and the absolute lowest was not selected. Sometimes it's some reasoning like well Skanska already built these 7 bridges so they can more easily build the next 5 even though their bid is 4% higher.
nychuman t1_j7ln94j wrote
Lowest leveled bid.
PsuedoSkillGeologist t1_j7km2ih wrote
This is logical to you?
For a general contractor to win a $3B job and from the get-go. Drag their feet. Hoping it’ll lose money, so they can sue the owner and get MAYBE 20 cents on the dollar?
SuperTeamRyan t1_j7koc2z wrote
Yes.
Underbid > get contract > start work > make slow progress > go over budget > still get paid as essential infrastructure is essential.
PsuedoSkillGeologist t1_j7kwflz wrote
Ok. I think I see your confusion now. As a general rule of thumb most companies, in every industry, across the entire globe don’t try to lose money on their work.
[deleted] t1_j7kz6pn wrote
[removed]
Jeff3412 t1_j7kzqo3 wrote
You talking about change orders from a contractor or from a design consultant?
The design consultation are the ones making the specs(In my experience not actually on the MTA job I did) and drawing sets that are supposed to give the contractor all the information they need to bid on the project. If that information is incomplete then the consultants really need to raise the alarm before they issue documents for bid or there's no point in bringing in outside consultants.
I say that about the specs because when I have worked on an MTA job instead of us writing the specs as we usually do they gave us a huge master spec that the MTA uses for all jobs and we just included word for word the relevant sections. I never felt more useless on a job. They essentially paid us to tell them what parts of their own specs to use which is something they could have easily done themselves.
PsuedoSkillGeologist t1_j7m0xgl wrote
A Change order is a shared contract change. It's the legal amendment of the contract to reflect the changes made to the work.
A Design consultant is not writing the specifications per se (assuming we're talking about Civil projects and that there are no special specifications). What happens, as you've pointed out, is that we're conforming the drawings to the agency's state specifications. These will change agency by agency with a lot of overlap. Sometimes the DDC will use the NYSDOT's specifications and vice versa.
Why re-invent the wheel. This is all public domain as well, there would be no need to write a specification unless the drawings require special specifications.
I've only every work for Civil construction, we would never be expected to write specifications but more to conform to their state issued ones.
There's too much bloat in this industry. I come from a scientific background. I tend not to accept 'that's just the way it is' as we continue on an unproductive role. Something has to change in the lowest bid sphere.
Of course there's Best Bid and Design-Build which seems to be a step in the right direction, but it comes with its own set of special failures.
I'm rambling at this point but just to summarize, yes you're absolutely right. Contracts are written for the contractor to conform to their specifications, which opens risk to the Owner when their specifications can not be met.
seenew t1_j7m25zn wrote
can y'all please fix this. it's embarrassing.
PsuedoSkillGeologist t1_j7m9iee wrote
I wish man.
philmatu t1_j7lbv1w wrote
I see time and time again that the agency doesn't have adequate staff (both in numbers and competency) to create clear requirements and contracts. This leads to vendors bidding for that set of requirements and a markup (to deal with the agency's incompetency), then when the project fails, change orders ensure further revenue streams. Then the agency does soul searching to figure out where it went wrong. It's a vicious cycle that costs all of us in the end.
PsuedoSkillGeologist t1_j7lz9w9 wrote
Without a doubt. I’d have no consultations if owners got their shit together.
I’ve presenting risk sharing models at ASCE that I believe would be the best solution for differing site conditions and design flaws. Even the questions at the end of the presentation were adversarial.
Every Job has change orders. And every owner and contractor seems to be looking for ways to make or save money. Both sides want to shift risk instead of addressing the issue that COs WILL happen. Instead of working out the semantics beforehand on what constitutes a ‘shared change’ they live in denial until they’re hiring consultants and design engineers to prove their side right. Once the smoke clears. The only profitable parties were the lawyers and consultants.
Nobody, and I mean that literally, Nobody can predict how the earth will behave in subterranean NYC. Meaning that you will always have a DSC. Why not accept this upfront and share the risk? Why? Because the owner wants to claim means and method and the contractor wants to pretend like they didn’t foresee the CO.
It’s all reactive instead of proactive. Because you can’t claim you didn’t see it coming if you try to be proactive.
Keep in mind this is a very broad generalization. Every CO is different. Some are slam dunks by the contractor and some are just wishful thinking.
The truth is that it’s never one party’s fault. But it is one party’s responsibility to build the structures. That means there’s an inherent opposition in what is supposed to be civic duty.
philmatu t1_j7m154o wrote
Surprisingly in 2011 my agency hired some MIT grads to design a system internally and become the integrators... mind you this system failed 6 times before. That model was so successful and cheap that it was transferred to 10 other projects, but most of the engineers left and weren't replaced with equally intelligent people. I'm the last of that wave and I'm simply too overwhelmed and overworked to keep up with the contract demands, so stuff naturally slips through the cracks. I care, but there isn't enough of me to keep up. As a result, many contracts are going up in cost and COs are happening, simply because I don't have time (nor resources) to create proper requirements to meet the deadlines imposed on me. It's purely become reactive. I agree
PsuedoSkillGeologist t1_j7mcsqi wrote
Sorry you gotta deal with this man. Why is it happening? I keep seeing the same names moving up to higher agency positions and the people I felt were competent engineers are now going Private or working for the contractors.
It’s a problem on both ends and of course my experience is anecdotal. But it seems like they push away talent to the higher paying private sector because they’d rather get 2 incompetent engineers for the price of 1 competent one.
Either way I appreciate what you do. I know it’s extremely difficult. And my resentment against agencies (much like corporations) is in their leadership. Those that seem to be ‘cruising’ when the reality is they have the ultimate responsibility to taxpayers.
Same can be said with my side. The nefarious GCs that intentionally start a project anticipating COs and find ways to double dip on contract work and CO work. They ruin it for everyone that believes in the concept of civic duty.
SleepyHobo t1_j7nx196 wrote
I work with contractors all the time on private and public projects. A lot of the time, especially on public projects, the change order is the result of nefarious intentions on the contractor's side to squeeze as much money as possible out of the owner because the government pays out big once a project is in the construction phase. CSI Format Specs were born out of the result of gross, shady contractors and increase project costs.
Lack of oversight leads to shit like this:
​
- Public contracts go to the lowest bidder i.e. the lowest common denominator. So you're already off to a bad start.
- Contractor (bidder) intentionally bids as low as possible, hiring consultants to substitute as much equipment and materials as physically possible to decrease their bid. If you're lucky, sometimes they "accidentally" miss things in the contract and try to get a change order for those things later on, delaying construction.
- Contractor will go behind the designer/engineer/architect's back straight to the owner or your client, violating the chain of command set up in the contract mind you, and say "Hey I can do Z instead of X and save you (and the contractor themselves) $$$$!" Owner/Client then comes to you and is eager to move forward with this substitution or design change which puts pressure on you to approve an inferior product that may not work as good.
- This usually leads to RFIs down the road from the contractor to the designers when something goes wrong with their substitution and throws their hands up saying "Well what should we do now??? You approved it!" even though the contract stipulates the contractor is responsible for added costs due to substitutions.
- Contractor has now spent a shit ton of money on consultants that was not part of their bid. They now need to make money on the contract and recoup the costs of the consultants.
- Contractor will continuously wear designers/architects/engineers down, sending in submittals that keep getting rejected for the same reason hoping they just relent. Sometimes they just give you submittals that have the completely wrong products for the spec or are just massively incomplete. They never send the full submittals if you do a partial approval.
- Contractor will submit products for review that don't meet the specs 99% of the time. Sometimes they change a minor detail that you can easily miss during review. Boom. They want a change order for the correct product. Nah sorry, you submitted a substitution. That's on you Mr. Contractor. Get bent.
- Contractors generally install things however they want, treating design drawings (the contract) as recommendations. Time after time I see contractors cut corners to save costs violating the contract. When these cuts get caught in inspections, it constantly delays construction.
- Will submit products for approval, but not buy them and secretly substitute with something else.
- Will not install equipment with proper clearances even though the design accounted for them. Here comes the RFIs, change orders, and inspection failures!
- The worst contractor I saw was for a brand new HVAC system for a building.
- He just reused the existing system, installed a few pieces of flexible ductwork, and put in some cheapo Home Depot fans (not powered or ducted) hoping he'd get away with it and call it a day. LOL. Lawsuit.
- Will just not install items that allow for a complete, operational system.
- Change orders pour in as a result of a contractor's inexperience in installing projects of certain designs. They don't know how to do it so they think they deserve more money to figure out how.
I really could go on and on. Can I also say that CBRE is the worst consulting group I've ever worked with?
[deleted] t1_j7kxcq8 wrote
[removed]
ken81987 t1_j7qod4h wrote
The subway costs 10x more than it should because the MTA didn't anticipate change orders well enough? Sounds unrealistic
Viewing a single comment thread. View all comments