https://www.springfieldmo.gov/5572/Division-Street-Reconstruction
PROJECT DETAILS:
Construction Estimated to Begin: Summer 2022
Anticipated Duration: 1 year
Contractor: Hartman & Co.
Engineering Design: Crawford, Murphy, and Tilly (CMT)
Construction Cost:
$4.7 million
Funding Source:
1/4-cent Capital Improvement Sales Tax
1/8-cent Transportation Sales Tax
Project Manager:
Andy Haase
ahaase@springfieldmo.gov