Submitted by Cooch98 t3_127nu65 in pittsburgh
I work for the county and we just had a large meeting yesterday about the Hot Metal Bridge. Currently the county and consulting parties are discussing design ideas on just about every detail possible. The designs should be finalized by the end of the year and construction to make it a pedestrian, cycling bridge should start next spring, and tenitivley should open to the public by summer of 2025. However, were still gonna need to get a lot more funding for this project which could delay the project, so I'd aim for a 2026 summer opening. Ask any questions you'd like and I'll try to answer the best I can.
PGHxplant t1_jef3z8j wrote
What is the north end going to connect to? The Duck Hollow trail ends more than a mile away and really isn't useful for much anyway. Besides that, it would be extremely helpful to have a safe and convenient way from the GAP to Swissvale Station. Biking across the Rankin Bridge and getting to the East Busway is a nightmare.